The Eco House
Controlled Asbestos Removal
“The earlier you commission an asbestos survey, the better. It gives you time to get comparable quotes, assess your options, and, if high-risk notifiable asbestos is identified, plan for the HSE notification period, crew mobilisation, and full removal under controlled conditions. All of this has to be done before demolition begins, so if you have vacant possession, don’t delay.”
— Oliver Steele-Perkins, Chartered Construction Manager
Preparing for Safe Removal
The project has entered a critical phase of site preparation, covering temporary infrastructure, safety measures, and ecological responsibilities. Asbestos removal is being carefully planned and managed in line with HSE regulations — a vital step before demolition can begin.
Following the required 14-day notification to the Health and Safety Executive (HSE), we mobilised on-site as scheduled and in line with the overall project programme. The asbestos-containing materials identified in the pre-demolition survey included external soffits and fascias, which necessitated full enclosure.
Controlled and Compliant Methods
In accordance with the Control of Asbestos Regulations 2012, a licensed contractor was appointed to undertake the works, ensuring that all procedures followed strict legal and environmental protocols.
A purpose-built enclosure was constructed to fully wrap the bungalow below the roofline, maintaining negative pressure within the work zone throughout the removal process. Air monitoring was carried out continuously, and a dedicated decontamination unit was installed on-site to manage personnel movements safely.
Monitoring, Waste Management & Site Safety
Viewing panels were set up to allow safe observation of the removal process (two of the photos on this page were taken through these panels), while a clearly defined waste route ensured all contaminated material was double-bagged and disposed of in line with hazardous waste regulations.
This setup demonstrates the correct approach to licensed asbestos removal, controlled, monitored, and fully compliant from start to finish.
Asbestos removal isn’t just a regulatory step – it’s a critical part of the pre-construction roadmap. On all our projects, we programme asbestos surveys and removal well in advance of demolition. This ensures we remain compliant, keep the site team and public safe, and avoid delays. Upon completion, certification is issued and included in the Health & Safety file – a key requirement.
Planning a New Build?
Lets Get It Right from the Start
Building your own home is a major investment, and the early decisions matter most. If you’re planning a new build and want professional guidance on procurement, planning, and cost control, we can help.
Whether you're just starting out or already in the design phase, we offer structured support to make your build smoother, smarter, and less stressful.
Guided Pathways
-
Plan It
Plan It equips you with the knowledge, tools, and structured processes to confidently design, budget, and prepare your homebuilding project, ensuring a smooth and well-managed build.
-
Build It
Build It equips you with the expertise, guidance, and step-by-step processes to manage your construction project effectively, ensuring quality, cost control, and timely completion.
-
Certify It
Certify It equips you with the knowledge and processes to navigate final inspections, compliance, and certification, ensuring your project is completed with the documentation needed to validate your investment.